Sylvain Pioch

Eco-design of Marine Infrastructures


Скачать книгу

for negative impacts. The aim is to make infrastructures “transparent” to the landscape and its ecological function (Rytwinski et al. 2016).

      Thus, over the past 50 years, planners have had to develop new approaches to meet this requirement to avoid, reduce as much as possible (or at least below a “significant” threshold) and finally offset the inevitable or irreducible residual impacts of any project. However, even though the regulations seem to be robust, if we look at the results in France, let us be clear, the record has been catastrophic since the introduction of the EIA in 1976 (Act no. 76-629 of July 10, 1976). According to Bigard et al. (2017), more than 77% of the definitions of ARO measures proposed in a sample of 42 terrestrial EIA files are wrong. At sea, Jacob et al. (2016) demonstrated, based on the study of 55 EIA files between 2000 and 2015 (France and DOM-TOM18), that 85% conclude that there is no significant residual negative impact of infrastructures on biodiversity. Furthermore, in the 15% of projects identifying the need for compensatory measures to repair biophysical losses, these are not actually implemented in the field (less than 10% of cases). These data and observations lead us to take a critical look at our own development (or “non-development”) choices.

      The impact study is an essential step in the environmental assessment of development projects and works. It is an approach designed to:

       – integrate environmental concerns into the design of a project by its promoter;

       – inform the authority called upon to decide whether to authorize its implementation;

       – inform the public by involving them in the decision-making process.

      1.4.1. Designing a better project for the environment

      The impact study is the means for the project promoter to verify that environmental concerns have been respected. As such, it must be an effective tool for integrating the environment into development projects and thus participate in the design of projects that respect people, landscapes and natural environments and are concerned with saving space, sparing species and limiting water, air and soil pollution.

      1.4.2. Informing the administrative authority on the decision to be taken

      The impact study is a prerequisite for an administrative decision to authorize or approve a facility, structure or development. It contributes to:

       – informing the competent authority, that is, the administrative authority (minister, prefect, mayor, president of a general council) that authorizes the work, about the nature and content of the decision to be made (authorization, approval or refusal of the project);

       – guiding the above in defining the conditions under which this authorization is given, for example, with regard to the implementation of measures to eliminate, reduce and offset for harmful effects;

       – controlling a posteriori the respect of the commitments made by the project owner, for example, by ensuring a follow-up of the consequences of the project on the environment during the implementation and operation phases.

      2) Baseline data collection (step 2/6): the objective in this step is to provide ex ante the environmental status of a site. This baseline is based on data from the biological, physical, landscape and human environment of the site before the project is implemented. It must provide sufficient data to identify, evaluate and prioritize the possible effects of the project on the environment and to allow for the rehabilitation of the site at the end of the operation.

      3) Screening (step 3/6): this step consists of assessing, through multi-criteria analysis, all the possible alternatives of the project design and sites to select a preferred alternative with the least environmental impact, excluding alternatives with an unacceptable impact. It also prepares for addressing the significant impact with steps 4, 5 and 6.

      4) Impact prediction and assessment (step 4/6): at the intersection of the initial state and the technical characteristics of the project, the EIA includes “an evaluation of the direct and indirect, temporary and permanent effects of the project on the environment, and in particular on the fauna and flora, the sites and landscapes, the soil, water, air, the climate, the natural environment and biological balance, the protection of property and cultural heritage and, where appropriate, the convenience of the neighborhood (noise, vibrations, odors, light emissions) or on hygiene, health, safety and public health” (Article R. 122-3 of the French Environmental Code).

      6) Impact monitoring (step 6/6): finally there is the impact monitoring step. It consists of an EIA follow-up by determining the protocols for monitoring the effects of the project and the mitigation measures over a variable period of time depending on the project, but including minimal monitoring before the start of the work (analysis that can be carried out during the initial state), monitoring during the construction phase, monitoring during the exploitation phase and, in the case of temporary occupation of the public maritime domain (PMD), monitoring following the dismantling of the exploitation unit (offshore wind farm, underwater pipeline, etc.). If necessary, monitoring also focuses on the effectiveness of offset measures (specific monitoring).

      It should be noted that the preparation of an EIA is an iterative process and these six hierarchical sequences do not constitute successive, compartmentalized stages. In order for the EIA to serve as an effective decision-making